Remove
existing fiberglass shower unit
-
Remove
old shower plumbing fixtures and drain
-
Thoroughly clean and seal concrete floor
-
Apply
two layers of tar paper to the three shower walls
from floor to ceiling.
-
Repair
hot and cold water pipes and install shutoff valves
on each pipe.
-
Install
the new shower control valve and shower head pipe.
-
Build the
front shower lip using 2x4's and wonder board.
-
Attach
wonder board to all three shower walls with screws,
leaving holes for shower head pipe and shower
control valve.
-
Cover
and seal all wonder board joints.
-
Apply
tile to three walls from ceiling to 3 rows above
floor.
-
Install the
four support shelves in the shower corners.
-
Grout all
the wall tile.
-
Install
rubber shower pan material to floor and glue eddge
together.
-
Install the
new shower drain.
-
Pour several
inches of concrete into the shower pan and form the
sloping surface so water flows to the drain.
-
Apply the
floor tile.
-
Finish
cutting and applying the bottom rows of wall tile.
-
Apply tile
to the shower lip.
-
Do final
grouting of all tile and apply calking to all corner
joints.
-
Seal all
grout lines
-
Install the
plexiglass sliding shower door