Shower Tile Project

2002

Job Description
  1. Remove existing fiberglass shower unit

  2. Remove old shower plumbing fixtures and drain

  3. Thoroughly clean and seal concrete floor

  4. Apply two layers of tar paper to the three shower walls from floor to ceiling.

  5. Repair hot and cold water pipes and install shutoff valves on each pipe. 

  6. Install the new shower control valve and shower head pipe.

  7. Build the front shower lip using 2x4's and wonder board.

  8. Attach wonder board to all three shower walls with screws, leaving holes for shower head pipe and shower control valve.

  9. Cover and seal all wonder board joints.

  10. Apply tile to three walls from ceiling to 3 rows above floor.

  11. Install the four support shelves in the shower corners.

  12. Grout all the wall tile.

  13. Install rubber shower pan material to floor and glue eddge together.

  14. Install the new shower drain.

  15. Pour several inches of concrete into the shower pan and form the sloping surface so water flows to the drain.

  16. Apply the floor tile.

  17. Finish cutting and applying the bottom rows of wall tile.

  18. Apply tile to the shower lip.

  19. Do final grouting of all tile and apply calking to all corner joints.

  20. Seal all grout lines

  21. Install the plexiglass sliding shower door

 

   